7-Eleven Clarkson Fuel & Electrical Project

LOCATION: Western Australia

SERVICES: Electrical | Fuel Systems

DATE: January 2025

Overview

Lovegrove completed the fuel and electrical works for Bella Build & Design at the 7Eleven Clarkson development.

Scope & Details

The project included excavation and installation of 180kL of underground fuel storage, supporting four fuel products, together with the installation of three 8-hose PEC fuel dispensers.

Lovegrove also completed the associated fuel pipework, with all pipework, including third-party infrastructure, comprehensively tested as part of the works. Extensive drainage works were also undertaken across the site.

Ground conditions presented a key challenge, with significant rock encountered during excavation. Despite the additional excavation requirements, the tank installation was successfully completed over a 10-day period.

The site was completed and handed over in March 2025.

Gallery

Ready to start your project?